The first building of the iLOT industriel Charny will be located on chemin de Charny and will have a surface area of 40,000 square feet. Its location is shown on the map below.
Work in progress
Site preparation :
- Schedule : Fall 2023 to spring 2024.
- October 2 to 4, 2023 : Arrival of machinery.
- October 5, 2023 : Start of work.
- Week of November 27, 2023: Start of the winter waiting period (no work) to allow natural soil compaction.
- IT IS FORBIDDEN TO USE THE LAND ON FOOT OR WITH ANY TYPE OF VEHICLE. PRIVATE LAND.
- IT IS FORBIDDEN TO PRACTICE ACTIVITIES ON THIS PRIVATE GROUND (snowmobiling, snowshoeing, sliding, etc.).
- STEEP SLOPES – RISK OF FALLING.
- May 2024: Development work resumes.
Hours of work
Except in exceptional circumstances, Monday to Friday, 7am to 5pm.
Upcoming work
Construction of the first building | Scheduled completion date: spring to fall 2024.
Nous privilégions le respect du milieu et une entière disponibilité pour répondre aux interrogations et préoccupations que vous pourriez avoir. En tant que développeur, nous souhaitons réaliser notre projet dans le respect de nos voisins.
Questions
If you have any questions about our development, you can refer to our website www.ilotindustriel.com, or contact our Community Relations Manager, Genevieve Tremblay. She can be reached by e-mail at info@ilotindustriel.com or by telephone at 833-839-5461.